Sunday, December 5, 2010

More Progress...

More progress this past week.  The machining for the entire slotbot is done except for a few minor tweaks.  In the coming week we have 6 hours of mill time reserved and we expect that to be more than enough to make final adjustments and get our machine up and running.  

Here's a brief list of what remains to be done:
Add e-clips to all axles
Extend motor wires
Solder on banana clips (if possible)
Finish adding holes to scoring arm (to remove weight)
Elongate the scoring arm by a few inches
Test, test, test!

This will be another busy week but it's exciting to see everything coming together.

Some parts:

Spring pin into the wall of the scoring arm to constrain axle

Both spring pins are visible here

Mack.  What more can be said?

A very artistic arrangement of cart axle pillows

Customized nuts to clear the gears of the gear train (We used the grinder on these)

Pillows and bolts lined up for assembly

Adding lightness to the scoring arm

In summary, spring pins rock!  We've successfully used them to constrain the axle and to constrain two gears.  I highly recommend them for all your medium duty pinning needs.

Till next time,

Lost Cause

No comments:

Post a Comment